Walk past the Waterfront Brisbane site on Eagle Street and you're looking at office moves planned years out, with law and advisory firms signed on to that tower before construction started.
Your move won't need that kind of runway. Still, I walk into moves where the lease is signed and the builder's booked, with IT services pencilled in for the week before, and the line I hear is "We'll get you in once the walls are up."
By then, your data points and comms cupboard have already been fixed in place at rough-in, when the sparky ran cable and the walls were sheeted over it. Every point in the wrong spot becomes a wall to chase open, so here are the IT services I'd book first.
The short version
Book your IT services at lease signing, before the fit-out drawings are signed off, because data points and the comms cupboard get locked in at rough-in. Order business internet two to three months out and test the new floor before staff arrive.Â
What’s in here
When should I bring my IT services provider into an office move?Â
Bring in your IT services provider when you sign the lease, before the fit-out drawings are signed off.
After that, the drawings stop being a plan and become the build. Your floor plan locks in where every data point and the comms cupboard go, whether they're labelled as IT or not. A practice manager sees desks and walls on those drawings, so I read them for the IT, checking every desk has a point and the cupboard has its own circuit and cooling.
The cost of getting it wrong shows up at rough-in. Before the walls are sheeted, moving a data point is a quick word with the sparky. Once they're lined, the same change means chasing the wall open and paying twice for the same cable.
I'd rather settle this at the design meeting than off the defects list, so get your IT provider to mark up the drawings first.

What IT do I need sorted before the fit-out starts?Â
Before the fit-out starts, you need your network designed into the floor and your business IT services on order.
Both have a deadline. The network has to go in before the builder closes the ceiling, and services need ordering early enough to beat carrier lead times.
What needs to go into the walls and ceiling?Â
Cabling and power go in before the ceiling closes, including the runs for Wi-Fi and security. The equipment itself goes up later.
Beyond the cabling, I'd run a Wi-Fi survey before the ceiling tiles go in, so the cable runs land where the access points need to sit. Access control and CCTV run on your network too, so they need data and power points drawn in, with spares for growth.
What do I need to order ahead of the move?Â
Internet, phone lines and replacement hardware all need ordering before the fit-out starts. That leaves time for delivery, so everything's installed and tested before your team arrives.
I’d sort every device into what moves, what’s replaced and what’s ordered new. Swap laptops due for replacement now so they only move once and start sourcing and setting up new hardware early.
Internet has the longest lead time of the lot, so I'd lodge it first.
What affects how long it takes to move my business internet in Brisbane?Â
Plan on a two-to-three-month runway for moving business internet in Brisbane, in line with NBN’s advice on relocating your business.
The move itself can take weeks. What pushes it to the full runway, or past it, comes down to what’s in the building and what you’re ordering.
What if my new office already has NBN connected?Â
If your new office has a working NBN connection, getting your service live can take as little as five minutes, depending on the service.
I’d check the NBN technology and whether the service is active the day you sign. A floor with no active service needs a new connection and an installation appointment, which adds more weeks in my experience.
What if NBN equipment has to move during my fit-out?Â
Moving NBN's equipment catches firms out, because only NBN can do it.
If your fit-out removes a wall carrying NBN’s gear, NBN’s relocation works process allows up to four weeks to scope the job before construction, which generally takes 50 business days or more.
What else adds time to my internet move?Â
Enterprise Ethernet, number porting and the Christmas slowdown all add time to an internet move.
NBN builds Enterprise Ethernet to order, so lodge it the week you sign. Porting your phone numbers adds days on top, while carriers and builders both slow down over Christmas and January.
Add those up, and if you’re moving in January, managing your internet and phone move should be under way by October or November.

How do I keep downtime low on moving day?Â
A written cutover plan keeps downtime low on moving day by setting the order of the switchover.
I won't promise zero downtime on a move, and I'd be wary of an IT provider who does. I plan for a short, predictable window instead, set by how the offices overlap and how the new one is tested.
Should I run both offices at once?Â
If your leases overlap, run both offices in parallel, even for a few days.
Your team keeps billing from the old floor while the new one gets tested. Then switch over a quiet weekend.
What should I test before my staff arrive?Â
Before staff arrive, test the new floor the way your team will use it on Monday.
For the firms I look after through IT support for professional services firms, the 4-step test below covers the systems your team can't bill without. A technician stays on site the first morning, because a fault fixed at 8.15am beats a ticket at 9.Â
4 things to test before you move inÂ
- Log in to practice management at both ends of the floor.Â
- Print through secure release.Â
- Call the main number from a mobile and transfer it.Â
- Open a client file over meeting room Wi-Fi.Â
If that test passes, your team starts Monday like any other week.Â
SummaryÂ
Your move won’t run on a tower’s timeline, but the same rule applies. The services get planned before the walls go up. If "We'll get you in once the walls are up" comes up in your planning, you'll know it's too late. With IT booked at lease signing, the drawings carry the right points before rough-in and your internet goes on order with months to spare. Testing before move-in handles the rest.
If your fit-out plans aren't locked in yet, let's go over the drawings together before they are.Â
Frequently asked questionsÂ
How much will office relocation IT cost me in Brisbane?Â
Â
I'd price it off your fit-out drawings, since they show how much cabling and hardware the move involves. Any number before then is a guess.Â
Â
Cabling is the biggest swing I see. A floor where the last tenant's points already line up with your desk’s costs far less than one that needs rerunning end to end.Â
Â
Hardware is the other variable, and it’s where sorting your devices earns its keep, because you only replace what's due. I'd also treat the move as a one-off project cost, kept separate from your ongoing IT services and support.Â
Can I keep my phone numbers when I move offices?Â
Â
Porting runs on the carriers' timeline, so I'd lodge it once the new address is confirmed and time the switch for your move weekend.Â
Â
Before you start, list every number the business owns, direct dials included, because a missed direct dial is the one a long-standing client still rings. If you're moving to Microsoft Teams or 3CX calling at the same time, your numbers can port onto the new system, so clients dial the same number on Monday and reach you at the new desk. Â
What happens to the IT equipment and data at my old office?Â
Â
I’d test a restore from that backup before the move, so a server knocked on the trolley doesn’t cost you a client file.Â
Â
Leave the NBN connection box behind, because it belongs to NBN and may not work at your new address. Check your make-good clause too, in case the landlord wants old cabling stripped out of the comms cupboard and ceiling before you hand back the keys.Â
Who should coordinate my IT with the builder during the fit-out?Â
Â
They'll support the comms cupboard and network long after the builder leaves, so they should sign off where it all goes.Â
Â
In practice, that means your IT provider gets every revision of the drawings and a seat at the design meetings that touch data or power. When the electrician has a question about a data point, the answer comes from your IT provider, and your practice manager isn't left guessing. Your builder still runs the program, but the IT decisions inside it have an owner.Â